Topic

Time and Work

Time and Work - Work efficiency, working together, alternate work, pipes and cistern problems

Learning Content

⏱️ What is period and work?

The relationship between the amount of time it takes to complete a job and the amount of that workPeriod and work(Time and Work) accounts explain.

📌 Basic concepts
Comment Explanation
Work Total work done. Generally let's assume 1 unit
Time Time required to complete the work (days/hours)
Efficiency Amount of work done in a day/hour
Men Number of people employed
🔗 Basic relationships
Work = Capacity × Duration
W = E × T
relationship Explanation
If one completes the work in n days 1 day's work = 1/n share
If 1 day's work = 1/n n days to complete the entire work
Capacity of A : Capacity of B = m : n Period of A : Period of B = n : m
💡Important:More capacity → less time (inverse ratio)
📊 Ratio relationships
factor Relationship with work ratio
People (M) More → more work direct ratio
Days (D) More → more work direct ratio
Hour (H) More → more work direct ratio
Efficiency (E) More → Less time The opposite ratio
M₁ × D₁ × H₁ × E₁ / W₁ = M₂ × D₂ × H₂ × E₂ / W₂
🔢 LCM Method (Best Method)

It is easy to calculate the LCM of the period as total work.

Steps:
1. LCM of all periods = total work
2. 1 day's work of each = total work / period
3. 1 day's work done together = addition of separate works
4. Total period = Total work / Cumulative work

Example:A - 10 days, B - 15 days

Total work = LCM(10,15) = 30 units

1 day of A = 30/10 = 3 units

1 day of B = 30/15 = 2 units

Together 1 day = 3+2 = 5 units

Total period = 30/5 =6 days

📚 Key Codes
Code Meaning English
W Work Work
T/D Duration / Days Time / Days
E ability Efficiency
M People Men
H hours Hours
🚰 Pipes and Cistern
Type Explanation Code
Inlet Filling the tank + (addition)
Outlet Emptying the tank - (Subtraction)
Leak Water comes out - (Subtraction)
💡Note:Pipe accounts and job accounts follow the same formula!
💡 Things to remember
  • If one finishes in n days:1 day's work = 1/n
  • Capacity ↑ → Duration ↓(counter ratio)
  • People ↑ → Period ↓(counter ratio)
  • Working together:1/A + 1/B = 1/T
  • Working against:1/A - 1/B = 1/T
  • LCM method:Very simple & fast!

📐 Period and Work Formulas

All necessary formulas for TNPSC Exam!

📌 Basic formulas
Work W = E × T Capacity × Duration
1 day work = 1/n If completed in n days
Full working days = 1 ÷ (1 day's work)
👥 Working Together
If A is a day and B is b day, together:

1/T = 1/a + 1/b

T = (a × b) / (a ​​+ b)
persons formula
A + B T = ab/(a+b)
A + B + C 1/T = 1/a + 1/b + 1/c
A – B (opposite) T = ab/(a-b) [a > b]
🔄 Alternate Days
If A and B work together:

2 day's work = 1/a + 1/b

Total Days = 2 × (Total Work / 2 Days Work)

Note:Watch out who starts first!

👷 Men and Days
M₁ × D₁ = M₂ × D₂(if work is equal)

M₁ × D₁ × H₁ = M₂ × D₂ × H₂(including hours)
situation formula
Work is equal M₁D₁ = M₂D₂
Work varies M₁D₁/W₁ = M₂D₂/W₂
Including hours M₁D₁H₁/W₁ = M₂D₂H₂/W₂
📈 Efficiency Formulas
Efficiency ratio = inverse ratio of time

If A:B capacity = m:n, then A:B duration = n:m
A is x% more efficient than B Duration of A = Duration of B × 100/(100+x)
A is x% less efficient than B Duration of A = Duration of B × 100/(100-x)
💰 Wages
Wages = proportional to work done

A:B wage = A:B job = A:B skill

Example:A - 10 days, B - 15 days, total pay ₹5000

Capacity ratio = 1/10 : 1/15 = 3:2

Salary of A = 5000 × 3/5 = ₹3000

Salary of B = 5000 × 2/5 = ₹2000

🚰 Pipes & Cistern
situation formula
2 filling tubes 1/T = 1/a + 1/b
1 fill + 1 empty 1/T = 1/a - 1/b (full > empty)
If there is leakage 1/T = 1/Fill - 1/Leak
Filling tube → + (Positive)
Drain pipe / leakage → - (Negative)
🔢 LCM method formulas
Step 1:Total work = LCM (of all periods)
Step 2:1 day's work of each = total work / period
Step 3:Cumulative 1 day's work = sum/subtraction of separate works
Step 4:Duration = Total Work / Cumulative 1 Day Work
⚡ Special formulas
situation formula
A+B = T₁, A+C = T₂, B+C = T₃ A+B+C = 2/(1/T₁ + 1/T₂ + 1/T₃)
A alone 1/A = (1/T₁ + 1/T₂ - 1/T₃)/2
If A works for n days Remaining work = 1 - n/a
Duration of x stock job T = x × total duration
📊 Major relationships table
A days B days together (ab/a+b)
2 2 1
3 6 2
4 4 2
5 10 10/3 = 3.33
6 12 4
10 15 6
12 18 36/5 = 7.2
15 20 60/7 ≈ 8.57

📝 Tenses and Work - Solved Examples

10 Important Questions for TNPSC Exam

Question 1: Basic – Two together

Question:A completes a piece of work in 12 days and B in 18 days. If both of them work together, in how many days will they finish?


Solution (LCM method):

Total work = LCM(12, 18) = 36 units

1 day's work of A = 36/12 = 3 units

1 day's work of B = 36/18 = 2 units

Together 1 day = 3 + 2 = 5 units

Period = 36/5 =7.2 days = 7 days 4 hours 48 minutes


Formula Method:T = ab/(a+b) = (12×18)/(12+18) = 216/30 =36/5 days

Question 2: Three together

Question:A - 10 days, B - 12 days, C - 15 days. If all three join?


Solution (LCM method):

Total work = LCM(10, 12, 15) = 60 units

1 day of A = 60/10 = 6 units

1 day of B = 60/12 = 5 units

1 day of C = 60/15 = 4 units

Together 1 day = 6 + 5 + 4 = 15 units

Period = 60/15 =4 days

Question 3: If one leaves

Question:A and B together finish in 6 days. A alone finishes in 10 days. A leaves after working together for 4 days. In how many days will B complete the remaining work?


Solution:

A+B together 6 days, A alone 10 days

B alone: ​​1/B = 1/6 - 1/10 = (5-3)/30 = 2/30 = 1/15

∴ B alone will finish in 15 days

Total work = LCM(6, 10, 15) = 30 units

A+B 1 day = 30/6 = 5 units

In 4 days = 4 × 5 = 20 units (completed)

Remainder = 30 - 20 = 10 units

1 day of B = 30/15 = 2 units

Required for B = 10/2 =5 days

Question 4: Shift work

Question:A - 20 days, B - 30 days. In how many days will it be completed if A starts from the first day and works in shifts?


Solution:

Total work = LCM(20, 30) = 60 units

1 day of A = 60/20 = 3 units

1 day of B = 60/30 = 2 units

In 2 days (A+B) = 3 + 2 = 5 units

60 units to complete = 60/5 × 2 = 24 days

But let's check:

In 22 days = 11 rounds = 55 units

23rd day A work = 3 units, total = 58

24th Day B Work = 2 units, Total = 60 ✓

24 days

Question 5: Persons and Days

Question:15 men complete a piece of work in 20 days. How many people are needed to finish in 10 days?


Solution:

M₁ × D₁ = M₂ × D₂

15 × 20 = M₂ × 10

M₂ = (15 × 20) / 10 = 300/10 =30 people

Question 6: Skill difference

Question:A is 50% more efficient than B. If B completes a work in 18 days, in how many days will A complete it?


Solution:

Efficiency of A = Efficiency of B + 50% = 150%

Capacity ratio A:B = 150:100 = 3:2

Period ratio A:B = 2:3 (inverse ratio)

If B = 18 days, A:B = 2:3

A = 18 × 2/3 =12 days

Question 7: Pipe and tank

Question:A pipe fills the tank at 12 o'clock. B tube empties at 18 hours. If both are open, at what time will it be full?


Solution:

Total capacity = LCM(12, 18) = 36 units

1 hour of A = +36/12 = +3 units (complements)

1 hour of B = -36/18 = -2 units (empties)

Together 1 hour = 3 - 2 = +1 unit

Period = 36/1 =36 hours

Question 8: Leak

Question:The tap fills the tank at 6 o'clock. If there is a leak it fills up at 8 o'clock. At what time will the leak clear itself?


Solution:

Pipe 1 hour = 1/6

Pipe + leak = 1/8

Leakage = 1/6 - 1/8 = (4-3)/24 = 1/24

To empty the leak =24 hours

Question 9: Pay distribution

Question:A will complete the work in 6 days, B in 8 days. How much for A if they work together and earn ₹2800?


Solution:

Capacity of A : Capacity of B = 1/6 : 1/8

= 8 : 6 = 4 : 3

Total share = 4 + 3 = 7

Wages of A = 2800 × 4/7 =₹1600

Salary of B = 2800 × 3/7 = ₹1200

Question 10: Additional persons

Question:20 men will complete the work in 30 days. If 5 men leave after 10 days, in how many days will the remaining work be completed?


Solution:

Total work = 20 × 30 = 600 man-days

Completed in 10 days = 20 × 10 = 200 man-days

Remaining work = 600 - 200 = 400 man-days

Remaining persons = 20 - 5 = 15 persons

Days required = 400/15 =26⅔ days ≈ 27 days

📚 Additional practice questions
  1. If A - 15 days, B - 20 days, together =60/7 ≈ 8.57 days
  2. 12 persons 18 day → 9 persons =24 days
  3. Pipe 4 o'clock fill, 6 o'clock empty → together =12 o'clock
  4. A:B capacity = 5:3, B = 15 day → A =9 days
  5. A 10 days, B 15 days, ₹3000 → A wages =₹1800

⚡ Period and Work - Crossroads

Super Tricks to Save Time in TNPSC Exam!

🚀 Trick 1: LCM method - exponential solution
Always use the LCM method!

1. Total work = LCM (periods)
2. 1 day's work = total work / period
3. Together = joint, against = waste

Example:A - 6 days, B - 8 days

Work = LCM(6,8) = 24

A = 4, B = 3, together = 7

Period = 24/7 =3 3/7 days

🚀 Trick 2: Two together - direct formula
T = (a × b) / (a ​​+ b)

"Multiplication Division Addition"
a b Together with T
2 3 6/5 = 1.2
3 6 18/9 = 2
4 6 24/10 = 2.4
5 10 50/15 = 10/3
6 12 72/18 = 4
10 15 150/25 = 6
🚀 Trick 3: Find B alone
A+B together on T day, A alone on A day:

B alone = (a × T) / (a ​​– T)

Example:A+B = 6 days, A = 10 days

B = (10 × 6) / (10 - 6) = 60/4 =15 days

🚀 Trick 4: Converter works - quick method
A, B conversion work (A first):

Calculate 2 day's work → Calculate complete rounds → Check balance

Quick Method:

Work = LCM, 2 days work = a + b

Rounds = Work / (a+b) × 2

🚀 Trick 5: The man-day formula
M₁ × D₁ = M₂ × D₂

"Total work = persons × days" (constant)

Example:10 people 12 days → 15 people how many days?

10 × 12 = 15 × D₂

D₂ = 120/15 =8 days

🚀 Trick 6: Efficiency Ratio = Inverse of Time
Capacity A:B = b:a(If term A:B = a:b)

Example:

A = 10 days, B = 15 days

Capacity A:B = 15:10 = 3:2

Wages A:B = 3:2

🚀 Trick 7: % Capacity → Duration
A is x% more efficient than B:
Duration of A = Duration of B × 100/(100+x)

A is x% less efficient than B:
Duration of A = Duration of B × 100/(100-x)
Efficiency % Period ratio
25% more 4/5 = 0.8 times
50% more 2/3 times
100% more (double) 1/2 times
🚀 Trick 8: Pipe Account Shortcut
Filling tube → + (Positive)
Vacancy / leakage → - (Negative)

Do it like a working account!

Example:Fill 4 hours, empty 6 hours

Work = LCM(4,6) = 12

Fill = +3, Empty = -2

Together = 3-2 = +1

Period = 12/1 =12 o'clock

🚀 Trick 9: Rest work account
If A works for n days:
Completed work = n/a
Remaining work = 1 - n/a = (a-n)/a

Example:A completes in 12 days and works in 4 days

Done = 4/12 = 1/3

Remainder = 1 - 1/3 = 2/3

🚀 Trick 10: Duration for x stock job
x share of work = x × total duration

Example:A 15 day full work, 2/5 part work?

Period = 15 × 2/5 =6 days

📊 TNPSC Frequently Asked Categories
Question type Crossroads
Two together T = ab/(a+b)
Three together LCM method
If one leaves Calculate the remaining work
man-day M₁D₁ = M₂D₂
Tubular tank Fill +, Empty -
Wages Efficiency ratio
💡 Important memory tips
  • 1 day's work = 1/n(if completed in n days)
  • Together: 1/a + 1/b
  • Against: 1/a - 1/b
  • T = ab/(a+b)- Two together
  • M₁D₁ = M₂D₂- man-day
  • Capacity ↑ → Duration ↓
  • LCM method = fast solution!
  • Pipe: Fill +, Empty/Drain -
🎯 Quick reference table
A day B day along with LCM
2 4 4/3 4
3 6 2 6
4 12 3 12
5 20 4 20
6 12 4 12
8 12 24/5 24
10 15 6 30
12 18 36/5 36
DISCLAIMER

This is an independent educational initiative. Not affiliated with TNPSC.
Please verify official sources before appearing for exams.